Ageing instrumentation and obsolete control systems present ongoing challenges for nuclear power stations, particularly where reliable gaseous discharge monitoring must be maintained alongside changing operational and maintenance requirements. The challenge is modernising these systems without unnecessary disruption to existing plant infrastructure, while improving reliability, alarm functionality and long-term maintainability.
AMS Nuclear delivers targeted EC&I upgrades that address obsolescence, retain compatibility with existing systems and introduce practical improvements, including on-site calibration capabilities that reduce maintenance costs.
At Hinkley Point B (EDF Energy), the Sulphur-35 (S-35) and particulate gaseous discharge monitoring systems required modernisation to address recurring instrumentation faults, ageing control equipment and limitations in back-up alarm functionality.
AMS Nuclear developed a comprehensive upgrade solution incorporating new Total Oxidation Units (TOUs), VA520 thermal mass flowmeters, replacement pump control logic and dedicated alarm annunciators. The proposed solution also included a bespoke flowmeter test rig to enable on-site calibration, reducing the need for routine instrument replacement and associated costs.
Designed around existing plant interfaces and supported by a modular approach to manufacture and testing, the upgrade provided a practical route to improved monitoring reliability, operational visibility and long-term system maintainability.
Overcoming Reliability and Obsolescence Challenges Without Disruption
The existing systems were increasingly affected by instrumentation limitations and ageing control equipment. Periodic faults required the use of mobile back-up units, which, while effective in maintaining monitoring capability, did not provide alarm signals to the central control room. This reduced operational visibility during maintenance or fault conditions.
In addition, key flow measurement instruments could not be calibrated on site. This led to routine replacement at significant cost and introduced inefficiencies into maintenance planning.
The challenge was clear: deliver a robust, modernised solution that improved reliability, restored full alarm functionality and reduced lifecycle cost – without introducing unnecessary disruption to existing plant operations.
Engineering a Maintainable, Future-Ready Monitoring Solution
AMS Nuclear approached the project as a targeted modernisation exercise, combining system redesign with practical improvements in maintainability and operability.
At the centre of the solution was the development and deployment of new Total Oxidation Units (TOUs); self-contained radionuclide sampling systems designed for accuracy, control and ease of use. These units incorporated:
- Controlled sample flow with integrated pressure and temperature monitoring
- High-performance furnace systems with fail-safe protection and trip functionality
- Local alarm annunciation with provision for remote signalling to plant systems
- Flexible installation options, including static and mobile configurations
Legacy flow measurement technology was replaced with modern thermal mass flowmeters, delivering improved accuracy, totalised flow measurement and compatibility with existing PLC interfaces. This ensured continuity while significantly enhancing performance.
To address obsolescence within the control system, AMS Nuclear removed legacy PLC hardware and implemented new control logic using modern, maintainable components. This included:
- Automated pump changeover functionality
- Dedicated alarm annunciators for clear operator feedback
- New instrumentation, including pressure transmitters, trip amplifiers and digital indicators
A key innovation was the introduction of a bespoke thermal mass flowmeter test rig, enabling on-site calibration and verification. This removed the need for routine instrument replacement and provided a sustainable long-term maintenance solution.

“We focused on solving the root cause, not just replacing equipment. By enabling on-site calibration and improving alarm visibility, we’ve made the system easier to maintain and more reliable in operation.”
Senior Engineer, AMS Nuclear
Creating a Scalable Approach to Modernising Legacy Systems
This project highlights how targeted, well-engineered upgrades can deliver significant value across ageing nuclear assets without the need for full system replacement.
Key learning points include:
- Designing for maintainability reduces lifecycle cost and improves operational resilience
- Modular engineering and off-site testing enhance quality and reduce installation risk
- Incremental modernisation provides a practical route to address obsolescence in safety-critical systems
- Clear alarm strategy and operator interfaces improve human factors and operational awareness
These principles are directly transferable across the UK nuclear fleet, where similar challenges around ageing instrumentation and system reliability are common.
This case study reflects AMS Nuclear’s commitment to delivering clear, accountable engineering solutions, combining technical expertise with a deep understanding of client needs to support safe, long-term nuclear operations.