From Legacy Limitations to Long-Term Assurance
Maintaining reliable gaseous effluent monitoring is essential for nuclear power stations, particularly as environmental requirements evolve and existing equipment approaches the end of its operational life. The challenge is not simply replacing ageing sampling systems, but ensuring new equipment meets current regulatory standards while integrating with existing plant infrastructure. AMS Nuclear designs and builds bespoke particulate and iodine sampling systems that address these requirements, combining specialist instrumentation expertise with rigorous quality assurance, full documentation and long-term maintainability.
At Heysham 1 (EDF Energy), five particulate and iodine sampling cubicles within the Gaseous Effluent Monitoring System required replacement to support compliance with the station’s environmental permit and Best Available Techniques (BAT) requirements. AMS Nuclear delivered a design and manufacture solution for five bespoke sampling cubicles, engineered to BS ISO 2889:2010, Environment Agency Technical Guidance Note M11 and relevant electrical standards.
Working to QA Grade 2 requirements, with Safety Category 2 and Seismic Category 2 assurance, we provided the engineering design, manufacture, testing and documentation, with commissioning support included in our scope. The approach combined site-specific engineering with consistent quality and documentation requirements, providing a basis for future maintenance and similar upgrades across the nuclear fleet.