Project Overview

Client: EDF Energy – Dungeness B

Type: Plant Life Extension (PLEX)

Scope Of Supply: Design, Substantiation, Build, Test, Delivery

Key Deliverables: 16 off Solenoid Valve Control Panels and Backup Air Systems

The second phase of a 3-phase project saw AMS engineer a solution and subsequently deliver a series of solenoid valve control panels and air receivers to enable the actuation of the Automatic Boiler Depressurisation System (ABDS) valve actuators, as part of the Boiler Lifetime Improvements Project at Dungeness B.

Why AMS?

AMS had previous success with the delivery of phase 1 of the project (20 off bespoke instrument cubicles) and were placed in prime position to deliver phase 2 of the project, where AMS’ known expertise in pneumatics systems were utilised. 

AMS Nuclear Certifications

ISO 9001:2015
ISO 14001:2015
ISO 45001:2018
Cyber Essentials
Fit For Nuclear